1.西安交通大学未来技术学院,710049,西安
2.西安交通大学机器人研究院,710049,西安
3.陕西省智能机器人重点实验室,710049,西安
4.上海飞机制造有限公司,201324,上海
收稿:2026-06-11,
修回:2026-07-19,
录用:2026-09-19,
移动端阅览
孙羽芊, 徐俊, 张健琛, 等. 考虑人员动态配置的复杂系统装配多目标协同调度优化[J/OL]. 西安交通大学学报,2026-11-12. http://zkxb.xjtu.edu.cn/zh/article/179612427/.
SUN Yuqian, XU Jun, ZHANG Jianchen, et al. Multi-objective Collaborative Scheduling Optimization for Complex System Assembly with Dynamic Workforce Allocation[J/OL]. JOURNAL OF XI’AN JIAOTONG UNIVERSITY,2026-11-12. http://zkxb.xjtu.edu.cn/zh/article/179612427/.
孙羽芊, 徐俊, 张健琛, 等. 考虑人员动态配置的复杂系统装配多目标协同调度优化[J/OL]. 西安交通大学学报,2026-11-12. http://zkxb.xjtu.edu.cn/zh/article/179612427/. DOI:
SUN Yuqian, XU Jun, ZHANG Jianchen, et al. Multi-objective Collaborative Scheduling Optimization for Complex System Assembly with Dynamic Workforce Allocation[J/OL]. JOURNAL OF XI’AN JIAOTONG UNIVERSITY,2026-11-12. http://zkxb.xjtu.edu.cn/zh/article/179612427/. DOI:
聚焦复杂系统装配场景,针对任务优先关系复杂、人员资源受限以及排产周期与人员规模相互制约的问题,构建考虑人员动态配置的任务与人员协同调度模型。模型以任务网络、作业工时、技能匹配和班组容量为输入,通过多目标优化同时最小化排产周期和人员规模,并满足工艺优先、最低配员、技能适配、资源容量及交付周期约束。提出人员资源重构机制,通过逐步收缩班组人员资源边界并重新优化调度方案,刻画人员规模变化对任务并行关系、资源竞争状态和调度可行域的影响。在求解方面,采用启发式规则与改进NSGA-Ⅱ算法相结合的两阶段方法,首先利用最小作业人数与最迟完成时间组合规则生成初始解,随后引入自交叉、自适应变异和延迟可行化策略,提高强约束条件下的搜索效率和可行解保持能力。基于某飞机制造企业机身对接阶段的1 242个装配任务开展验证,并构造不同任务规模和交付压力场景。结果表明,在初始人员配置下,所提方法将排产周期由1 370 h缩短至968 h;在实际产线交付周期要求下,最小可行人员规模为113人;在300~1 500个工序规模下均能获得可行方案,人员优化率不低于32.86%。所提方法能够有效协调排产周期与人员投入,并具有较好的规模适应性和求解稳定性。
To address the problems of complex task precedence relationships
limited workforce resources
and the mutual constraint between makespan and workforce size in complex system assembly scenarios
a task and workforce collaborative scheduling model considering dynamic workforce allocation is constructed in this study. The model takes the task network
operation time
skill matching
and team capacity as inputs
and simultaneously minimizes the makespan and the workforce size through multi-objective optimization
while satisfying the constraints of process precedence
minimum staffing
skill matching
resource capacity
and delivery lead time. A workforce reconfiguration mechanism is proposed
in which the team workforce resource boundary is progressively shrunk and the scheduling scheme is re-optimized to capture the impact of changes in workforce size on task parallelism
resource competition
and the scheduling feasible region. In terms of solution
a two-stage method combining heuristic rules with an improved NSGA-Ⅱ algorithm is adopted. Initial solutions are first generated using the combination rules for minimum workforce and latest finish time
and then self crossover
adaptive mutation
and delayed feasibility restoration strategies are introduced to improve the search efficiency and the ability to maintain feasible solutions under strong constraints. Validation were carried out based on 1
242 assembly tasks in the fuselage docking stage of an aircraft manufacturing enterprise
and scenarios with different task scales and delivery pressures were constructed. The results show that under the initial workforce configuration
the proposed method shortened the makespan from 1
370 to 968 time units; under the actual delivery lead time requirement of the production line
the minimum feasible workforce size was 113 people; feasible schemes could be obtained for operation scales of 300–1
500
with a workforce reduction of at least 32.86%. These findings demonstrate that the proposed method can effectively coordinate the makespan and workforce input and has good scale adaptability and solution stability.
李明星 , 张凯 , 苏意芬 , 等 . 分布式柔性智能制造系统联动管控架构与方法研究进展及展望 [J ] . 西安交通大学学报 , 2025 , 59 ( 12 ): 21 - 43 .
Li Mingxing , Zhang Kai , Su Yifen , et al . Synchronization architectures and methods for distributed flexible smart manufacturing systems: research progress and prospects [J ] . Journal of Xi'an Jiaotong University , 2025 , 59 ( 12 ): 21 - 43 .
Liu Ziwen , Liu Jianhua , Zhuang Cunbo , et al . Multi-objective complex product assembly scheduling problem considering parallel team and worker skills [J ] . Journal of Manufacturing Systems , 2022 , 63 : 454 - 470 .
江志斌 , 周利平 . 面向智能制造的生产运作管理: 挑战、科学问题、关键研究及部分新进展 [J ] . 工业工程 , 2024 , 27 ( 1 ): 1 - 9 .
Jiang Zhibin , Zhou Liping . Production and operation management for intelligent manufacturing: challenges, scientific issues, key research, and latest development [J ] . Industrial Engineering Journal , 2024 , 27 ( 1 ): 1 - 9 .
Gao Qinglin , Liu Jianhua , Li Huiting , et al . Digital twin-driven dynamic scheduling for the assembly workshop of complex products with workers allocation [J ] . Robotics and Computer-Integrated Manufacturing , 2024 , 89 : 102786 .
何家威 , 张朝阳 , 叶子健 , 等 . 面向复杂环境的人机协作装配意图识别方法 [J ] . 西安交通大学学报 , 2025 , 59 ( 12 ): 44 - 57 .
He Jiawei , Zhang Chaoyang , Ye Zijian , et al . Human-robot collaborative assembly intention recognition method for complex environments [J ] . Journal of Xi'an Jiaotong University , 2025 , 59 ( 12 ): 44 - 57 .
李涛 , 吴悠 , 李川东 , 等 . 面向复杂制造环境的任务驱动型产能评估方法与系统开发 [J ] . 工业工程 , 2025 , 28 ( 6 ): 159 - 171 .
Li Tao , Wu You , Li Chuandong , et al . A task-driven capacity evaluation method and system development for complex manufacturing environments [J ] . Industrial Engineering Journal , 2025 , 28 ( 6 ): 159 - 171 .
Xu Xun , Ji Tang , Zheng Pai , et al . Human-centric manufacturing: re-thinking, re-justifying, and re-envisioning [J ] . Journal of Manufacturing Systems , 2026 , 84 : 259 - 268 .
Wu Song , Wang Yang , Du Yu , et al . Resource-constrained multi-stage processing and assembly scheduling with sequential and batch operations [J ] . Journal of Heuristics , 2025 , 31 ( 4 ): 38 .
Zhao Haoyi , Huang Xiangming , Liu Guoliang , et al . Learning-based multi-objective hyper-heuristic algorithm for reconfigurable assembly line scheduling problems [J ] . PLoS One , 2026 , 21 ( 5 ): e0348884 .
Bao Zhongkai , Chen Lu , Qiu Kejun . An aircraft final assembly line balancing problem considering resource constraints and parallel task scheduling [J ] . Computers & Industrial Engineering , 2023 , 182 : 109436 .
Rohaninejad M , Vahedi-Nouri B , Hanzálek Z , et al . An integrated lot-sizing and scheduling problem in a reconfigurable manufacturing system under workforce constraints [J ] . International Journal of Production Research , 2024 , 62 ( 11 ): 3994 - 4013 .
Snauwaert J , Vanhoucke M . A solution framework for multi-skilled project scheduling problems with hierarchical skills [J ] . Journal of Scheduling , 2025 , 28 ( 3 ): 289 - 310 .
Ghamginzadeh A , Najafi A A , Khalilzadeh M . Multi-objective multi-skill resource-constrained project scheduling problem under time uncertainty [J ] . International Journal of Fuzzy Systems , 2021 , 23 ( 2 ): 518 - 534 .
Bao Nengsheng , Zheng Xiaoxun , Fan Yuchen , et al . Enhancing garment manufacturing efficiency through human-centered scheduling [J ] . Production Engineering , 2025 , 19 ( 5 ): 885 - 898 .
Zhang Jingyue , Fujimura S . An innovative meta–heuristic for balancing and scheduling human–robot collaborative assembly lines in Industry 5.0 [J ] . Journal of Industrial and Production Engineering , 2026 , 43 ( 1 ): 117 - 137 .
Wang Dongyuan , Qiao Fei , Guan Liuen , et al . Human–machine collaborative optimization method for dynamic worker allocation in aircraft final assembly lines [J ] . Computers & Industrial Engineering , 2024 , 194 : 110370 .
Wu Yinghui , Zeng Shaoyu , Li Bingbing , et al . A bi-objective approach for the multi-skilled worker assignment of a hybrid assembly line-seru production system [J ] . RAIRO-Operations Research , 2024 , 58 ( 2 ): 1187 - 1206 .
Yang Wenchao , Li Sen , Luo Guofu , et al . A real-time human–machine–logistics collaborative scheduling method considering workers’ learning and forgetting effects [J ] . Applied System Innovation , 2025 , 8 ( 2 ): 40 .
蒋权 , 魏静萱 . 用于动态柔性作业车间调度的实时调度方法 [J ] . 系统仿真学报 , 2024 , 36 ( 7 ): 1609 - 1620 .
Jiang Quan , Wei Jingxuan . Real-time scheduling method for dynamic flexible job shop scheduling [J ] . Journal of System Simulation , 2024 , 36 ( 7 ): 1609 - 1620 .
Yang Shiming , Meng Leilei , Ullah S , et al . MILP modeling and optimization of three-stage flexible job shop scheduling problem with assembly and AGV transportation [J ] . Chinese Journal of Mechanical Engineering , 2025 , 38 ( 1 ): 115 .
Kulaç S , Kiraz A . Collaborative robot integration in mixed-model assembly line balancing with ergonomic risk considerations [J ] . Flexible Services and Manufacturing Journal , 2026 : 1 - 40 .
杨震 , 高丰 , 刘检华 , 等 . 基于改进NSGA-Ⅱ算法的多阶段混合流水装配车间工人分配方法 [J ] . 机械工程学报 , 2025 , 61 ( 15 ): 417 - 440 .
Yang Zhen , Gao Feng , Liu Jianhua , et al . Multi-stage hybrid flow assembly workshop worker assignment method based on improved NSGA-Ⅱ algorithm [J ] . Journal of Mechanical Engineering , 2025 , 61 ( 15 ): 417 - 440 .
Padmavathi V , Kanimozhi R , Saminathan R . Digital twin driven smart factories: real time physics based co-simulation using edge a.i. and federated learning [J ] . Scientific Reports , 2025 , 15 ( 1 ): 43373 .
Chang Xiao , Jia Xiaoliang , Ren Jiahao . A reinforcement learning enhanced memetic algorithm for multi-objective flexible job shop scheduling toward Industry 5.0 [J ] . International Journal of Production Research , 2025 , 63 ( 1 ): 119 - 147 .
Singh P , Krishnan K , Boldsaikhan E . A review of production scheduling with artificial intelligence and digital twins [J ] . Journal of Manufacturing and Materials Processing , 2026 , 10 ( 1 ): 6 .
Artigues C , Hartmann S , Vanhoucke M . Fifty years of research on resource-constrained project scheduling explored from different perspectives [J ] . European Journal of Operational Research , 2026 , 328 ( 2 ): 367 - 388 .
Liu Chenghao , Wang Yanhong , Sun Lijia , et al . Data-driven approach for scheduling problems: a review [J ] . IAENG International Journal of Applied Mathematics , 2026 , 56 ( 2 ): 687 - 697 .
Ma Kangxin , Yang Changchun , Xu Haojie , et al . A fast-flexible strategy based approach to solving employee scheduling problem considering soft work time [J ] . Scientific Reports , 2024 , 14 ( 1 ): 6170 .
Wang Yulai , Lu Renzhi . A novel Multi-objective evolutionary algorithm for proxy-based energy-aware scheduling in aircraft assembly line [J ] . IEEE Transactions on Industrial Cyber-Physical Systems , 2026 , 4 : 82 - 93 .
Hu Jinhua , Zhu Jiyue , Sun Yanning , et al . Network-based two-stage robust scheduling strategy for the aircraft assembly system with uncertain duration [J ] . Computers & Industrial Engineering , 2024 , 188 : 109911 .
Zaghdoud R , Zidi I , Ben Rhaiem O , et al . A hybrid NSGA-II and delayed local search approach for home healthcare scheduling and routing optimization [J ] . Applied Soft Computing , 2026 , 191 : 114617 .